A groundbreaking ceremony for the new Helena High was scheduled for Tuesday, June 16, 2026. Credit: Courtesy of A&E and SMA Design

Helena voters last summer approved over $280 million in taxes for a new Helena High School, a new Kessler Elementary school and major renovations to Capital High School. 

Now, nine months later, and after architects, engineers, district trustees and other community stakeholders have weighed in, the building phase has begun, with the new HHS groundbreaking scheduled for Tuesday evening. 

With the goal of all three projects being under construction by the end of the year, school officials hope to have the facilities operational by the fall of 2028. 

Here is what Helenans can expect to see between now and then.

HELENA HIGH, PAL AND THE DISTRICT KITCHEN

The original Helena High School building, built in 1955, faces some of the district’s most significant infrastructure deficiencies, including failing water boilers and a sinking foundation. 

The new school will be built to the right of the existing building, with plans to continue using the original gym. Once the new HHS is completed and operational, the district will demolish the old building. 

The district hired Dick Anderson Construction as the general contractor and construction manager. The district also brought on A&E + SMA Design and NAC Architecture as the primary project designers. 

When the district first campaigned for the facility bond, officials anticipated needing about $167.4 million for the new school, construction of new space for the district’s alternative high school, Project for Alternative Learning (PAL), and the new district kitchen.

The early construction phase for HHS and PAL will last through mid-July and includes site preparation, organization and setting up construction equipment, fencing and bringing in other materials. 

Project architects also anticipate completing the project’s official construction documents by Aug. 11, which are needed for permitting and in the bidding process.

Primary construction will then begin and is expected to conclude in August of 2028. 

The district also launched a livestream of the construction site so viewers could track the building’s progress.

The district kitchen, originally housed in the Capital High campus, will soon have its own building on the same property as HHS. The district is expected to seek bids for the kitchen by next week, according to Tim Meldrum of SMA. 

KESSLER ELEMENTARY

Project architects anticipate breaking ground on the new Kessler Elementary building this October.
Credit: Courtesy of Mosiac Architecture

Kessler Elementary, a neighborhood school located on Helena’s west side, was built in 1936. The $42 million bond voters approved will fund an entirely new building on the same property. 

The district hired Mosaic Architecture and Crushing Terrell to design the new school, with plans to submit permit requests to the city by the first week of September. 

Golden Eagle Construction and Swank Enterprises were brought on for the project’s general contractor and construction manager.

The project team is about 50% through the building’s design and plans to break ground this October. 

CAPITAL HIGH

Major renovations will be done at Capital High after demolition work started recently. Credit: Courtesy of Slate Architecture and RTA Architects  

Capital High will be renovated, rather than demolished and rebuilt, and its students will still attend the school while construction is underway.

CHS was built in 1965 as a Catholic high school and was acquired by the school district in 1973. The building’s infrastructure needs about $14 million in deferred maintenance, along with security and electrical improvements and a new HVAC system. 

Slate Architecture and RTA Architects are leading the design for CHS, with Langlas & Associates as the project’s general contractor and construction manager. 

The high school renovation addresses the needed structural improvements and will begin with the design of temporary classrooms. Some demolition started last week. 

Temporary classrooms will be set up in the library wing, according to project architects. 

While demolition is underway, there is still design work to complete, according to project architects, and construction documents are expected to be completed by December. 

In-depth, independent reporting on the stories impacting your community from reporters who know your town.

LATEST STORIES

How Montana’s federal campaigns are funded

Montana’s federal candidates have arrived at the final stage of the general election largely fueled by individual contributions. National political action committee donations and contributions from congressional leadership committees also play a major role. Here’s a summary of the financial picture for each major candidate who raised at least $90,000 in individual contributions leading up to the Nov. 3 election, including where the bulk of their itemized donors reside.

First Nations celebrate Albertans’ decision to remain a part of Canada

The Blackfoot Confederacy, a coalition of tribes in Montana and Alberta, celebrated Albertans’ decision this week to remain a province within Canada. The “no” vote represents a long-sought victory for First Nations in Alberta, who brought a legal challenge and launched a public information campaign to thwart the secession. Alberta’s independence movement dates back to the Great Depression, though it gained popularity and legitimacy after a handful of events in recent years, including the COVID-19 pandemic and the election of Prime Minister Mark Carney.

Crow Legislature rejects bill to expand enrollment

After nearly two hours of impassioned debate, the Crow Tribe’s Legislature on Wednesday voted down a bill that would dramatically change who counts as a tribal member. The bill, brought by Chairman Frank White Clay, would have revised the tribe’s “blood quantum” standard, effectively making more people eligible for tribal citizenship. Supporters argued that the change was needed to ensure the continued existence of the tribe. Opponents expressed concern over straining federal funding.

JoVonne Wagner has been the Helena reporter for MTFP Local since 2023, where she covers elections, politics and community affairs. She also writes the Helena This Week newsletter. She originally came to Montana Free Press as a Legislative Fellow covering the American Indian Caucus. She is a graduate of the University of Montana School of Journalism, and previously interned at Buffalo’s Fire and ICT, formerly known as Indian Country Today. She has also contributed work to the Montana Media Lab. JoVonne is from Heart Butte and a member of the Blackfeet Nation. Contact JoVonne at [email protected].