The remains of the Columbia Falls Aluminum Co., are seen just north of Columbia Falls, on April 1, 2024. This site was designated a Superfund site by the EPA in 2016 and the agency is expected to release a final Record of Decision about its cleanup in the coming weeks. Credit: Justin Franz / MTFP

The owner of a sprawling, long-shuttered aluminum plant in Columbia Falls has agreed to pay $57.6 million to mitigate pollution associated with decades of aluminum smelting.

The U.S. Environmental Protection Agency released a statement Tuesday applauding an agreement with Columbia Falls Aluminum Company that outlines the cleanup objectives for one of northwestern Montana’s largest industrial sites.

The agreement comes nearly a decade after the EPA added the Columbia Falls Aluminum Company site to the National Priorities List, also known as the Superfund list. Under the agreement, CFAC will be responsible for mitigating toxic byproducts such as arsenic, fluoride and cyanide at the site, which was Flathead County’s largest employer in its 1970s heyday. Much of the waste will be consolidated at the site and capped with material designed to prevent pollutants from contaminating the surrounding soil and water.

Cyrus Western, the former Wyoming legislator who now oversees EPA’s Region 8 office headquartered in Denver, described the development as a “significant milestone” that will facilitate site redevelopment.

“In coordination with our federal, state, local and industry partners, EPA is advancing effective, protective solutions that safeguard human health and the environment,” Western said in a July 7 press release. 

About half of the smelting facility’s total footprint — the most polluted portion — is incorporated in the Superfund site. Developers have big plans for other areas of the site outside the official Superfund boundary. A 78-acre parcel area south of Aluminum Drive called Teakettle Heights is slated for a 421-unit residential development that would include a mix of apartments, townhomes and single family homes. Due to contamination concerns, the project developer plans to tie into city water rather than using groundwater to supply the units with water.

The 647-page agreement between CFAC and EPA is not yet final. It will be subject to a 30-day public comment period and another round of review by the U.S. District Court in Missoula before it’s considered officially adopted. As with other sites on the EPA’s Superfund list, the analysis and clean-up for the CFAC site is more of a marathon than a sprint. It’s not uncommon for the EPA and the corporations that own Superfund sites — which include some of the most polluted landscapes in the country — to spend decades addressing contamination concerns associated with legacy industrial operations.

The Columbia Falls Aluminum Company, which was Flathead Valley’s largest employer in the late 1970s, is located two miles northeast of  Columbia Falls.  Courtesy U.S. EPA

Columbia Falls became an aluminum smelting powerhouse in the 1950s due to its proximity to the hydroelectricity dams situated up and down the Columbia River Basin, which provided the site’s first owner, Anaconda Copper, with cheap, plentiful power.

Swiss commodities giant Glencore purchased the CFAC property in 1999. Glencore will put $57.6 million in a fund dedicated to the federal government’s “past and future response costs” as well as future costs the Montana Department of Environmental Quality incurs. 

“The start of active cleanup activities is a positive step toward addressing environmental impacts at the site and reflects a shared commitment by CFAC and local, state and federal partners to position the area for long-term and sustainable reuse,” Glencore President Cheryl Driscoll said in the EPA press release.

RELATED

‘We have one chance to get it right’

As the Environmental Protection Agency determines how to address the contamination left by a former aluminum plant — and a new owner eyes future development — a grassroots group in Columbia Falls is urging the federal agency to slow down.

A group of Flathead Valley citizens had pushed for the removal of the toxins (rather than the “waste in place” strategy that the EPA decided on), but the agency determined in its January 2025 record of decision that hauling the toxic material to an appropriate landfill would have incurred additional cost and risk. 

The 1,340-acre site borders the Flathead River to the south, Cedar Creek Reservoir to the north, Teakettle Mountain to the east and Cedar Creek to the west. Water contamination has been a major concern for Flathead Valley residents eager to see the area cleaned up.

This map illustration by the EPA shows the main plant as well as the landfills, sludge pond and percolating ponds that Columbia Falls Aluminum Company used at its sprawling smelter facility near the Flathead River.

Tony Haag, president of Coalition for a Clean CFAC, told Montana Free Press he’s encouraged that remediation is progressing. He plans to dive into the particulars of the agreement, officially known as a consent decree, so he can offer detailed comments. And he has questions: Will the EPA keep the public “in the loop?” Does the federal government have a rigorous strategy for monitoring pollution concentrations to ensure that the cleanup is meeting its stated objectives?

“We’re sort of in a new phase now,” Haag said, referencing the anticipated initiation of remediation. “Our goal now is to monitor that and make sure it’s done well.”

RELATED

EPA releases plan for cleanup of Columbia Falls Superfund site

The EPA’s plan for the Columbia Falls Aluminum Company site along the Flathead River comes 15 years after the plant closed and eight years after it was added to the national Superfund list. The plan largely reflects a draft version that was criticized by a local group that wanted the EPA to force the site’s owner, mining giant Glencore, to completely remove the contaminated soil.

Coalition for a Clean CFAC formed in 2024 to push EPA and Glencore to thoroughly clean up the site in order to support community health, enjoyment and economic development, and to protect the Flathead watershed. Haag said his group is urging the public to remain involved, noting that this may be one of the last opportunities they have to shape the Superfund site’s future.

EPA spokesperson Melissa Walther wrote in an email to MTFP that the agency anticipates CFAC will work on a design for remediation through the end of this year. 

“Due to construction schedules, EPA is unable to project a final timeline,” she said. “But the work could be done within the next two to three years.”

This story was updated on July 9, 2026, to adjust a typo from Thompson Falls to Columbia Falls, and to clarify the amount that Glencore will pay for CFAC remediation.

LATEST STORIES

High diesel prices squeeze Montana farmers

Near-record diesel prices are putting pressure on Montana farmers who depend on fuel to run combines, tractors and other equipment, and also increasing the cost of transporting goods once they leave the farm.

Amanda Eggert has covered energy, environment and public lands issues for Montana Free Press since 2021. Her work has received multiple awards, including the Mark Henckel Outdoor Writing Award from the Montana Newspaper Association. Born and raised in Billings, she is a graduate of the University of Montana School of Journalism and has written for Outside magazine and Outlaw Partners. At Outlaw Partners, Amanda led coverage for the biweekly newspaper Explore Big Sky. She is based in Bozeman. Contact Amanda at [email protected].